Upcoming activities
The following activities are scheduled to take place over the next two weeks:
- Establish perimeter erosion control (underway)
- Strip asphalt and remove existing structures within construction zone (i.e., light poles, parking gates)
- Begin relocation of crosswalks on Albany Street near the construction site in preparation of the sidewalk closing in front of the site
- Establish temporary water source for Community Garden located behind Albany Garage (N4)
Construction activity forecast August 21 – September 3*
*Please note that the schedule is subject to change due to weather and material delivery.